Capex forecasting
Why capex forecasts are inaccurate, and why the miss goes unmeasured
Overview
Ask a group controller how accurate last year's capex forecast was and you will get a number for the full year. Ask about the quarterly forecasts and the answer takes a week to assemble. The figures sit in four different files and an ERP export. Nobody ever put them in a line.
- Topic
- Capex forecasting
- Written by
- Weissr Capex Experts
- Published
- 17 September 2026
- Reading time
- 8 min read

The short answer
What is capex forecast accuracy?
Capex forecast accuracy is the measured difference between what a company forecast it would spend on its capital investments in a period and what it actually spent in that period. It applies to the spending forecast inside a live capital programme, the figure a group controller collects each quarter. It is what tells a CFO how much weight the capex guidance given to the market can carry.
Capex forecasts become inaccurate for several reasons, but optimistic estimation receives most of the attention. Teams estimate low, permits arrive late and suppliers slip. In its 2022 work on capital expenditure management, McKinsey found overruns against original cost and schedule estimates frequently passing 50 percent, across industries, public sector and private alike.
A less visible problem is that controllers rarely measure the error at all. Each new forecast replaces the one before it: the wrong figure disappears, and the evidence of how wrong it was goes with it. Most organisations discuss forecast accuracy. Very few calculate it.
Part of the optimism is psychology: teams estimate what a project should cost if it goes as planned, rather than what comparable projects actually cost. Part of it is incentive, since a lower figure stands a better chance of getting through the capex approval process. Either way it explains one estimate coming in low. It says nothing about why the same group comes in low again next year, and the year after.
In more than thirty years of working inside capex processes at industrial groups, we have yet to meet one that could produce last year’s quarterly forecasts without rebuilding them by hand.
The quarterly cycle
What happens to a miss after the quarterly review
A plant manager forecasts €6M for Q1 and spends €3.4M. What follows is the same almost everywhere: the gap shows up in the quarterly pack, the project manager attributes it to a permit that came late, the explanation is accepted because it is true, and the next cycle opens with clean figures. Twelve months on, the same site forecasts the same way. Everyone behaved reasonably. The lesson had nowhere to go.
McKinsey’s November 2024 study of mining and metals projects put roughly two-thirds of cost overruns and schedule delays down to weak initial assessment, and the remaining third to execution. Eighty-three percent of recent major projects in the sector ran into cost or schedule problems, with capex overruns above 40 percent.
Much of the error is therefore present before work begins, yet it can remain hidden through years of monthly cost reporting.
The estimate
Where the error actually enters
Operational people usually resist the idea that the damage is done at the estimate, and fairly so. Anyone who has run a capital project has watched costs move during execution: the contractor variation, the extra crane weeks, the scope that grew because the old line was in worse condition than the inspection suggested.
Execution feels like where money escapes because execution is where money is watched. Sanction the project and the machinery starts: monthly cost reports, commitment tracking, variation orders, a steering group asking awkward questions. An overrun in execution and tracking gets seen, escalated and eventually explained.
The estimate gets none of that. Someone produces it over a few weeks, under time pressure, with engineering that is nowhere near complete. It gets challenged in the approval meeting, adjusted and approved. From that moment it becomes the baseline, the figure everything else is measured against, and the one figure no one reopens. So the machinery spends three years measuring deviation from a number that was wrong on the day it was set. Which is also why most capex software is built around execution: that is where the visible pain is.
The repeat
Why the same miss comes back next year
Weak estimating explains where a single error starts. It leaves the harder question open, because plenty of misses have nothing to do with estimating at all. A permit slips four months and the money moves into next year: the total is right and the year is wrong. A site in Poland spends exactly what it forecast in zloty, the group reports in euro, the rate moved, and the board pack shows an overrun that happened entirely in the currency market.
Permits and exchange rates come from outside the company, and a capex system stops neither. The third cause sits inside. Forecasts come from the people delivering the projects, and those people are assessed on whether the plant came online. Whether February’s figure matched September’s reality never enters their appraisal. Where budget allocation runs on use it or lose it, the incentive points further the same way: a site that forecasts honestly and comes in under gets a smaller envelope next year.
For them a forecast is a statement of intent, and intent is not a measurement. Neither the appraisal nor the budget cycle gives anyone a reason to keep that figure long enough to learn from it.
The version problem
Where last quarter's forecast goes
In our study of 20 European capex organisations, 14 of the 20 ran their capex calculations on standardised in-house Excel templates. For several of them the template was the request form.
Every forecast cycle produces a version, and the version it replaces is rarely kept.
A new file replaces the old file, or a new column replaces the old column. Answering how accurate last year’s forecasts were then means reconstruction: find the old file, work out its scope, pull the matching actuals, align the currencies. For one investment that is an afternoon. For a portfolio of two hundred it stays on the list of things the team would do with more capacity, and after a couple of years the controller stops asking. The same study lists this among the most common mistakes in capital allocation: follow-up that is discussion-based rather than analytical, so the lessons are never gathered.
The cost
What an unmeasured forecast error costs
Contingency becomes a flat percentage. Without a record of which estimates ran low and which ran high, contingency cannot be sized by evidence, so it is set by convention. Most groups apply the same uplift to a greenfield build and a pump replacement. Capital then sits reserved against investments that were never going to need it. The money is not lost, but it remains unavailable, and on a €200M annual programme the frozen share is material.
Systematic bias stays invisible. A site that comes in 15 percent low every year is a different problem from a project hit once by a supplier failure. One needs its estimating method rebuilt, the other needs nothing at all. In the reporting they look identical, and both receive the same response. The explanation is accepted and the next cycle begins.
The board hears an apology rather than a control. “We were 12 percent over” invites scrutiny of the number. “We were 12 percent over, down from 19 last year, with the remaining gap in two categories” gives the board evidence of direction and cause. The same miss can then support a more useful discussion.
The feedback loop
How often the loop has to close
Capex software vendors, Weissr included, agree that the capex process needs a feedback loop, and in this market the feedback loop means the post-completion review. Compare delivered cost, schedule and benefit against what was approved, record what was learnt, carry it forward. It is sound practice, and it has earned its reputation.
The limitation is the interval. A post-completion review closes the loop once, at the end, and in practice on material projects only, since most groups staff the review function for the big ones and leave the rest. It reports after the capital is committed. It can establish that a project finished in 2024 was estimated 14 percent low. That may help when a comparable project next comes up for sanction, but it is too late to correct the forecast itself. Running a full review every quarter is not practical for most groups, and the finding would still arrive after the spend.
If the point of the loop is to correct estimating, it has to close on the rhythm the estimating runs on: every period, on every investment, regardless of size.
Weissr Capex closes the loop at that interval. Post-completion review runs as it does elsewhere in this market. Underneath it, the forecast that stood at each period close is kept rather than overwritten by the next cycle. Deviation is recorded when the period closes, and the remaining forecast is recalculated against it. These are the mechanics behind capex forecasting and financial control.
One change in the mechanics, and the series survives. The forecast that stood in February is still there in September, and the distance between them is a figure rather than an impression. At that point a capex forecast stops being an expression of intent and becomes a measurement with a known error. That version of a forecast, a CFO can put in front of a board.
Key takeaways
- Capex forecasts are inaccurate for two reasons: teams estimate optimistically, and the error is overwritten before anyone measures it.
- McKinsey puts about two-thirds of capex overruns in mining and metals down to weak initial assessment rather than execution. The estimate is produced once and never revisited, while execution is inspected monthly for years.
- Most capex processes replace each forecast with the next, so accuracy requires manual reconstruction and is rarely calculated.
- The cost shows up as flat contingency, undetected estimating bias and weak board reporting.
- Post-completion review closes the feedback loop once per project, after the money is spent. Closing it at every period close, on every investment, is what makes accuracy readable while the projects are still running.
Solution
Capex Forecasting & Financial Control
Budget, commitment, forecast and actual against the same investment, across every site and currency.
Product
Capital Budgeting
Forecast and actual held as separate series, recalculated at every period close.
Blog
The capex process
Six phases, five handovers, and where the reasoning behind the numbers disappears.
Product
Capex Management
Govern execution, commitment and close-out against the approved case.
By role
Group Business Controllers
Follow up budget, commitment and actual without rebuilding the pack.
By role
CFO & Finance Leaders
Give the board a capex number with a known error.
Follow Weissr on LinkedInfor new Capex Blog posts.
Keep reading
All Capex Blog posts
Capex maturity
How Mature Is Your Capex Process? Find Out in 3 Minutes
Signs your Capex process has not kept pace with the business, and a three-minute assessment to see where you stand.
Buyer's guide
Best capital planning software: a buyer's guide for finance leaders
How to tell capex, capital planning and project software apart, and ten criteria to check before you compare vendors.

CEO perspective
Capital Allocation is Your Strategy
Why the companies that outperform on capex will not be those that invest most, but those that allocate best and reallocate fastest.

CEO perspective
The Tail Wags the Dog: Your Capex Process Is Quietly Writing Your Strategy
Every approved project can have a positive NPV while the portfolio still takes the company somewhere leadership never chose.

Capex fundamentals
Capex vs Opex: the line that decides who gets to say yes
Capital expenditure and operating expenditure explained in plain language, with examples, a comparison table and the practical effect on financial governance.

Capex fundamentals
Capex, explained: what capital expenditure really means in practice
A plain-language introduction to capital expenditure: the categories, the vocabulary, and how capex actually moves through an industrial organisation.

Capex process
Inside the capex process: six decisions between a strategy and a built asset
How strategy, planning, budgeting, approval, execution and review connect, and why weak handovers undermine capital decisions.

Capex governance
Why capex approvals take months and what actually shortens them
A practical look at the capex approval process, where delays arise and how each stage should work.

Our story
The Weissr story: from capex advisory work to a Capex Platform
Where Weissr comes from: the founders, the methodology behind the book and how it became a platform for the whole Capex cycle.
Capex Maturity Assessment
What's yourCapex maturity level?
Answer a short set of questions on process, data, visibility and cash flow, and get a report showing your level in each area.
Take the assessmentCapex forecasting
Questions about forecast accuracy,answered directly.
What is capex forecast accuracy?
Capex forecast accuracy compares the forecast that stood for a period against what was actually spent in it. It can be calculated at investment level, at site level or across a whole portfolio, and it reads as a trend rather than a single result, which is why it needs several periods of history behind it.
Why are capex forecasts inaccurate?
Project teams estimate optimistically, and permits, suppliers and ground conditions move both timing and scope. Underneath that sits a second cause: each new forecast replaces the previous one, so the size of the last error is not recorded anywhere and the next estimate is made without it.
How do you measure capex forecast accuracy?
Keep the forecast that stood at each period close, record the actual for the same period against the same investment, and calculate the deviation. Across several periods that produces a series, which is what shows whether estimating is improving, holding or drifting. In Weissr Capex the forecast that stood at each period close is kept, so the series exists without anyone assembling it.
Does a currency movement count as a capex forecast miss?
In the group report it looks identical to one. A site that spent exactly what it forecast in local currency shows as over or under once the figures are consolidated at a different rate. Separating the two means comparing against the rate that applied when the budget was approved, rather than restating history at today's rate. The variance then splits into what the project did and what the currency did.
Is a post-completion review enough to improve forecast accuracy?
It is necessary, and on its own it falls short. A post-completion review runs once, at the end, typically only on material projects, and reports after the capital has been committed. It improves the next business case of a similar type. It does not tell the controller building this quarter's group forecast whether the current estimates are drifting. That needs forecast and actual held as separate series against the same investment, period by period.
Make capex forecast accuracya figure, not an impression.
See how Weissr keeps the forecast that stood at each period close and measures the distance to actual.
Book a demo